What will be the cost of M20 grade concrete?/How to calculate the cost of concrete having a 1:1.5:3 mix ratio?

 In this article, let us work out the cost of M20 grade concrete.



 

All the calculation part of the material required for concrete is covered in the separate article. So, before proceeding further, you have to go through that article 👇

Material estimation for M20 grade concrete./ Estimating cement, sand, & aggregates in 1 CUM. of 1:1.5:3 mix ratio (M20)concrete.


A.  Material cost:

The average ongoing market rate in India is considered for calculation purposes.


B.  Labor cost :

The labor rate for concrete ranges from INR 900/- to 1600/- per CUM.

Let us take the average rate of INR 1250/- for calculation purposes.


Now, let us calculate the cost of the M20 grade concrete per CUM in the table format.

Sl. no.

Item.

Qty.

Rate.

in INR.

Unit.

Cost

in INR.

1.

Cement

  8.06

380/-

Bags

  3062.80

2.

Sand

14.832

60/-

Cu ft

    889.92

3.

Aggregate

  29.664

  48/-

  Cu ft.

  1423.87

4.

Curing

Lump-sum

    250.00

5.

Miscellaneous

Lump-sum

    150.00

6.

                                                      The material cost =

 5776.59

7.

                                                       Add 5% wastage =

   288.82

8.

                                                   Total material cost =

 6065.42

9.

                                                                Labour cost =

 1250.00

10.

 The total cost of M20 grade concrete/ CUM =

7315.42

 

Note:

 1. The quantity of materials in the table is taken from the above-given article.

 2. To get accurate results, insert the ongoing market rate of labor & materials in your country or region.


The cost of M20 grade concrete per cu ft.

= [INR 7315.42/- ÷ 35.314]

( 1CUM = 35.314 cu ft.)

INR 207.15/- per cu ft.


For contractor:

If the concrete work is handed over to any contractor, then you have to add 10% extra as his profit.

The cost of M20 grade concrete work done by a contractor

    = [INR 7315.42/- + 10% of INR 7315.42/-]

    = [INR 7315.42/- + INR 731.54/-]

    = INR 8046.96/-  per CUM.


To go through rate analysis & cost-related articles, click here.