 Let us now calculate the cost of rubble soling as shown in the below drawing.


Given data:

Length of the rubble soling = 15 ft.

Width of the rubble soling = 8 ft.

The thickness of the rubble soling = 0.75 ft.


The total volume of the rubble soling

= [length × width × thickness]

= [15 ft. × 8 ft. × 0.75 ft.]

90 cu ft.

Before proceeding further, go through the article 👇

👀  What is rubble (boulder) soling? - their purpose & thumb rules in soling calculations.

So that you will understand the calculation concept clearly, without any questions.


A. Material calculation:

1.  Volume of  rubble stone:

The required vol. of stone 

= [1.25 × the vol. of  rubble soling]

= [1.25 × 90 cu ft.]

112.50 cu ft.


2. Volume of moorum:

The required vol. of moorum

= 15% of the vol. of rubble stone.

= [15 × 112.5 cu ft. ÷ 100]

16.875 cu ft.

B.  Labor calculation:

The labor rate per cu ft. of the rubble soling work ranges from INR 9/- to 15/- depending upon the region.

Let us consider an average rate of INR 12/- per cu ft.

The total cost of labor for rubble soling

   = total vol. of rubble soling in cu ft.  × labor rate/ cu ft.

   = 90 cu ft. × 12/-

   = INR 1,080/-

Note: Labor rate inclusive of moorum spreading, compaction, & water flooding.


Now, let us calculate the total cost of rubble soling in table format.

Sl. no.

Item.

Qty.

Rate.

in INR.

Unit.

Cost

in INR.

1.

Rubble stone

 112.50

        33/-

Cu ft.

   3,712.50

2.

Moorum

     16.88

      12/-

Cu ft.

       202.56

3.

Rent of compactor

  Lump-sum

       200.00

4.

Water for flooding

Lump-sum

       100.00

5.

Miscellaneous

Lump-sum

       100.00

6.

                                                      The material cost =

   4,315.06

7.

                                                       Add 5% wastage =

       215.75

8.

                                                   Total material cost =

   4,530.81

9.

                                                                Labour cost =

   1,080.00

10.

       The total cost of rubble soling work =

   5610.81

 

Note: To get accurate results, insert your regional market rate of materials & labor, in the above table.


a. The cost of rubble soling /cu ft.

= [total rubble soling cost ÷ total soling vol. in cu ft.]

= [5,610.81 ÷ 90]

= INR 62.34 /cu ft.


b. The cost of rubble soling /cum.

   = [62.34 × 35.3147]

  = INR 2,201.60 / cum.

( As 1cum = 35.3147 cu ft.)


Note:

 If the work is handed over to any contractor, you have to add 10% extra for his profit.

To go through rate analysis & cost-related articles, click here.

Thank you for going through this article. Have a good day😄.