Let us consider RR ( stone ) masonry wall for the calculation purpose as shown in the below drawing.
Given data:
Length of the stone masonry wall = 15 ft.
Height of the stone masonry wall = 7 ft.
The thickness of the RR masonry wall = 1.5 ft.
The total volume of the RR masonry wall
= [length × height × thickness]
= [15 ft. × 7 ft. × 1.5 ft.]
= 157.5 cu ft.
Before proceeding further, go through the article 👇
👀 . What is random rubble masonry? - Thumb rules in RR masonry calculations.
to understand the calculation procedure without any questions.
A. Material calculation:
1. Volume of rubble stone:
The required vol. of stone
= [1.25 × the vol. of RR masonry wall]
= [1.25 × 157.5 cu ft.]
= 196.875 cu ft.
2. Cement mortar:
The required dry vol. of cement mortar
= 40% of the vol. of RR masonry.
= [40 × 157.5 cu.ft. ÷ 100]
= 63 cu ft.
Let us build this wall in the cement mortar of a 1:6 ratio
a. The volume of the sand
= [{its ratio ÷ ( total ratio)} × dry mortar vol.]
= [{6 ÷ ( 6 + 1)} × 63]
= [0.8571 × 63]
= 54 cu ft. or
= 1.53 cum.
b. Volume of the cement
= [total dry mortar vol. - volume of sand]
= [63 cu ft. - 54 cu ft.]
= 9 cu ft.
As you know, one bag of cement = 1.226 cu ft.
Number of cement bags
= [9 cu ft. ÷ 1.226 cu ft.]
= 7.34 bags.
B. Labor calculation:
The labor rate per cu ft. of the RR masonry work ranges from INR 10/- to 16/- depending upon the region.
Let us consider an average rate of INR 13/- per cu ft.
The total cost of labor for RR masonry
= total vol. of RR masonry in cu ft. × labor rate/ cu ft.
= 157.5 cu ft. × 13/-
= INR 2,047.5/-
To go through rate analysis & cost-related articles, click here.
Now, let us calculate the total cost of RR masonry in table format.
Sl. no. |
Item. |
Qty. |
Rate. in INR. |
Unit. |
Cost in INR. |
1. |
Rubble stone |
196.88 |
35/- |
Cu ft. |
6,890.80 |
2. |
Cement |
7.34 |
380/- |
bag |
2,789.20 |
3. |
Sand |
54.00 |
60/- |
Cu ft. |
3,240.00 |
4. |
Curing |
Lump-sum |
200.00 |
||
5. |
Miscellaneous |
Lump-sum |
275.00 |
||
6. |
The material cost = |
13,395.00 |
|||
7. |
Add 5% wastage = |
669.75 |
|||
8. |
Total material cost = |
14,064.75 |
|||
9. |
Labour cost = |
2047.50 |
|||
10. |
The total cost of RR masonry wall = |
16,112.25 |
Note: To get accurate results, insert your regional market rate of materials & labor, in the above table.
a. The cost of random rubble masonry/cu ft.
= [total RR masonry cost ÷ total masonry vol. in cu ft.]
= [16,112.25 ÷ 157.5]
= INR 102.30 /cu ft.
b. The cost of random rubble masonry/cum.
= [102.3 × 35.3147]
= INR 3,612.70 / cum.
( As 1cum = 35.3147 cu ft.)
Note:
If the work is handed over to any contractor, you have to add 10% extra for his profit.