What will be the cost of plastering in a building?/ How to calculate the cost of internal plastering?

 Now, let us calculate the interior plastering cost of one room of a building as shown below.


Given data:

Width of the room = 14ft.

Length of the room = 16ft.

Height of the room = 10 ft.

One door of size = 2.5ft × 7.0 ft.

One window of size = 3ft × 4ft.


Area of a wall to be plastered

= [{(2nos × area of  front & back wall) + (2nos × area of sidewalls)} - {(door size) +( window size)}]

= [{(2nos × 14ft. × 10ft.) + (2nos.× 16ft. × 10ft.)} - {(2.5ft. × 7.0ft.) +( 3ft. × 4ft.)}]

=  [{(280sq ft.) + (320 sq ft.)} - {(17.5 sq ft.) +( 12 sq ft)}]

= [ { 600sq ft.} - {29.5 sq ft.}]

= 570.5 sq ft.


Area of the ceiling to be plastered

= [14ft × 16ft.]

= 224 sq ft.


The total area of plastering

= wall area +ceiling area

= 570.5 sq ft. + 224 sq ft.

= 794.5 sq ft.

Usually, the thickness of wall plaster ranges from 10mm. to 15mm. & the thickness of the ceiling plaster range is between 6mm to 10mm.

For the calculation purpose, let us consider wall plaster of a thickness of 12mm. & the ceiling plaster of 8mm. thickness.

Data considered:

Wall plaster thickness = 12mm =0.0394 ft.

Ceiling plaster thickness= 8mm = 0.0262 ft.

Let us make plaster of a 1:4 ratio. 


The total volume of the plaster

= [vol. of wall plaster + vol. of ceiling plaster]

=[ (area of wall plaster × thickness) + (area of ceiling plaster × thickness)]

= [( 570.5 sq ft.× 0.0394 ft.) + ( 224 sq ft. × 0.0262 ft.)]

= [22.477 cu ft. +5.869 cu ft.]

= 28.346 cu ft.


A. Material calculation:

Read the article, Calculating the quantity of materials in 1 cum. & 1cuft. of plastering mortar in different mix ratios.

Cement bag required per cu ft of plaster mortar = 0.217 bags

The volume of sand required/cu ft. of plaster mortar = 1.064 cu ft.

Note: The quantity of cement & sand/ cu ft. is taken from the above-mentioned article.


1. No. of  cement bags required 

      = vol. of plaster × bags/ cu ft.

      = 28.346 cu ft × 0.217 

     = 6.15 bags.


2. The volume of sand required 

= vol. of plaster × sand / cu ft.

= 28.346 cu ft. × 1.064

= 30.16 cu ft.


B.  Labor calculation:

The labor rate per sq ft. of the internal plastering ranges from INR 10/- to 15/- depending upon the region.

Let us consider an average rate of INR 12/- per sq ft.

The total cost of labor for plastering

   = total area of plaster in sq ft.  × labor rate/ sq ft.

   = 794.5sq ft. × 12/-

   = INR 9,534/-


Now, let us calculate the total cost of plastering in table format.

Sl. no.

Item.

Qty.

Rate.

in INR.

Unit.

Cost

in INR.

1.

Cement

6.15

400/-

Bags

  2460.00

2.

Sand

30.16

60/-

Cu ft

  1809.60

3.

Chicken mesh

Lump-sum

    200.00

4.

Miscellaneous

Lump-sum

    150.00

5.

                                                      The material cost =

 4619.60

6.

                                                       Add 5% wastage =

   230.98

7.

                                                   Total material cost =

 4850.58

8.

                                                                Labour cost =

 9534.00

9.

                                 The total cost of plastering =

14,384.58

 

The cost of internal plaster/sq ft.

= [total plastering cost ÷ total plastered area]

= [ 14384.58 ÷ 794.5]

= INR 18.10/sq ft.


The cost of internal plaster/cu ft.

= [total plastering cost ÷ total plastered vol.]

= [14384.58 ÷ 28.346]

= INR 507.46/cu ft.

To go through rate analysis & cost-related articles, click here.

Thank you for going through this article. Have a good day😄.