First, we will calculate the total quantity of materials required for the construction of different item works.

The total number of cement bags for shed work.

Note: The value i.e. mentioned below are taken from all 6 parts of the series.

       = [for PCC + for masonry + for  plastering + for flooring]

       = [7.75 +  1.85 + 2.0952 + 1.789]

       = 13.4842 bags 

The total volume of sand required for the shed work in cu ft.

     = [for PCC + for masonry + for  plastering + for flooring ] 

     = [19.02 + 13.578 + 10.2734 + 8.7963]

     = 51.667 cu ft.

The total volume of aggregates required in the shed work

     = for PCC

     = 38.04 cu ft.


Let us find out the material & labor cost for the construction of a shed.

Material cost:


 Sl.No.   Description        Quantity    Rate      Unit      Amount

  

 1.    Boulder for plinth          85.5         23       cu ft.      1966=50
         & foundation

 2.   Total cement bags     

       for shed work             13.484       400        bag      5393 =60     

 3.    Total sand for 

       shed construction      51.667         60        cu ft.     3100=02            

 4.   Total aggregates for 

       shed construction       38.04          54       cu ft.      2054=16

 5.    Flooring tile                16.0         150        no.        2400=00  

 6.   Roofing sheets              4.0        1920        no.       7680=00 

 7.   Rectangular steel                          

       section                     53.748         47        kg          2526=00

 8.   RCC door                   1.0         1600       no.        1600 =00

 9.   RCC window             1.0          650       no.           650 =00 

10.  Concrete blocks     374.0            30       no.        11220=00

              Total material cost for shed work =  INR  38,590=28



           Labor cost:

Sl.No.   Description        Quantity      Rate      Unit      Amount

 1.     Earthwork excavation          

        for the shed                  102.0            5        cu ft.        1017=60

 2.    Boulder soling               85.5            4        cu ft.         342 =00

 3.    PCC work                     43.23           12      cu ft.          518=00

 4.    Muroom filling             15.75            4       cu ft.            63=00

 5.   Tile flooring                  63.0               9       sq. ft.         567=00

 6.   Block masonry           177.875           24     cu ft.        4269=00                 

 7.   Plastering                   245.25                7      sq. ft         1716=75

 8.   Roofing sheet fixing   144.0                8     sq. ft.        1152=00

 9.  Fixing a door                  1.0               200       no.          200=00

10. Fixing a window           1.0                150       no.          150=00


                                 Total labor cost for shed work = INR  9,994.00


    The total construction cost of the shed work = INR 48,584.28


Note: The rate of the material & labor changes according to their availability in different regions.


The construction cost of the shed per sq. ft

         = [total cost of shed ÷ plinth area]

         = [48584.28 ÷ 80 ]

         = INR 607.3 / sq ft.        


         PART 6     👈 BACK   

To go through rate analysis & cost-related articles, click here.

Share:

No comments:

Post a Comment

Translate

Blog Archive

popular posts

Recent Posts

Google search