Let us make a boulder soling of 9" thick ( 0.75 ft.) for the footing as shown below.
= ( 0.75 ft ÷ 2.5 ft.) × 140 cu ft.
(by volume ratio with excavation)
= 0.30 × 140 cu ft.
= 42 cu ft.
(by volume ratio with footing excavation)
= 0.132 × 140 cu ft.
= 18.48 cu ft.
From the above drawing, depth of excavation = 0.9166 ft.
PCC thickness = 4" ( 0.33ft.).
(by volume ratio with plinth beam excavation)
= 0.36 × 145.365 cu ft.
= 52.33 cu ft.
The total volume of the PCC for the compound wall
= Vp1 + Vp2
= 18.48 cu ft.+ 52. 33 cu ft.
= 70.81 cu ft.
Calculating the quantity of materials in PCC.
Let us make PCC in the 1:2:4 mix.
Quantity of cement bags required for PCC
= 17.942 bags × ( 70.81cu ft ÷ 100 cu ft.)
= 12.70 bags.
The volume of sand required for PCC
= 44 cu ft. × ( 70.81cu ft ÷ 100 cu ft.)
= 31.156 cu ft.
The volume of aggregates required for PCC
= 88 cu ft. × ( 70.81cu ft ÷ 100 cu ft.)
= 62.31cu ft.
Note: The value taken for the calculation purpose is derived in the article "Calculating the quantity of materials in 100 cu ft. & 1 cum. of M15 (1:2:4 ) grade concrete".