All about civil construction knowledge- PARAM VISIONS

Bar bending schedule of a plinth beam. / BBS of a plinth beam.

 BACK 👈PART-2

Let us prepare a BBS for the simple plinth beam as shown below.


Given data :

Clearspan of the beam = 2500 mm.,  beam size 300mm × 380 mm.

Top & bottom rebar dia. = 12 mm.,  number of bars = 4 nos.

Stirrups 8 mm.∅ @ 150 mm c/c.,  clear cover =25 mm. on all the sides.


The cutting length of the main bar

=  [(2 times × Ld) + inner distance between columns - (2nos. × 2d ) ]

(Let us take development length Ld as 40d, and we have taken 2d for the 90° bend deductions.)

= [ ( 2 × 40 × 12 mm.)+ 2500 mm. - ( 2 nos. × 2 × 12 mm ) ]

= [ 480 mm + 2500 mm - 48 mm]

= 2932 mm i.e. 2.932 m.


Cutting length of the stirrup

= [2nos. × { (a +b )} + (hook length) -  (90° bend) - (135° bend )]




Where a = beam width - 2 × cover, & b = beam depth - 2 × cover

= [2 nos.  × { ( 300 mm - 2 × 25mm.) + ( 380 mm - 2  × 25mm )} + (2nos ×10d ) - (3 nos. × 2d ) - (2 nos. × 3d) ]

Here, 10d is taken for hook length.

We have deducted 2d for 90° bend -3nos., & 3d for 135° bend -2nos. as shown in the above drawing.

= [2 nos.×{ ( 250 mm ) + ( 330 mm ) } + (2nos. ×10 × 8mm) - ( 3 nos. × 2 × 8mm ) - ( 2 nos. × 3 × 8 mm.)]

= [2 nos. × { 580 mm } + 160 mm - 48mm - 48mm.]

= [1160 mm + 160 mm - 96 mm.]

= 1224 mm i.e. 1.224 m.


Number of stirrups 

= ( plinth beam length ÷ stirrup spacing ) + 1

= (2500 mm. ÷ 150 mm) +1 

= 16.66 + 1

= 17.66 nos.

By rounding off, the no. of stirrups required = 18 nos. 


To know the checklist for beam shuttering, go through the article👇

👀. Checklist for beam shuttering./What are the points to be checked in beam formwork?


Now, let us prepare a BBS table for the plinth beam.


sl.    bar                    dia.     no.     length    total      weight       total   
no.                        ( mm)                 (m.)     length     kg/m      weight

1.  main bar              12         4    2.932         22.8         0.89     20.292

2. stirrups                 8         18    1.224      22.032       0.395       8.702

                                                     Total weight of bars  =  28.994 kgs.

                                                    Add 3% wastage          = 0.869  kgs.

                                             Grand total of rebars  =  29.863 kgs.       