Bar bending schedule ( BBS ) of footing./ Cutting length of bars in a column footing.

 Let us prepare the bar bending schedule of the footing for the below-given drawing. 






Given data :

footing length = 2000 mm., width = 1500 mm. , depth = 300 mm.

rebar diameter = 12 mm.  spacing =150 mm, cover = 50 mm on all the sides.


No. of bars along x-direction

  = [ {( footing length ) - ( 2 × cover )} ÷ spacing ] + 1

  = [ {( 2000 mm.) - ( 2 × 50 mm.)} ÷ 150 mm.] +1

  = [ { 1900 mm } ÷ 150 mm. ] +1

  = 12.67 +1 

  = 14 nos.

( by rounding off )


No. of bars along y-direction

  = [ {( footing width ) - ( 2 × cover )} ÷ spacing ] + 1

  = [ {( 1500 mm.) - ( 2 × 50 mm.)} ÷ 150 mm.] +1

  = [ { 1400 mm } ÷ 150 mm. ] +1

  = 9.33 +1 

 = 10 nos.


Cutting length of the bar along the x-direction

=  [ {bar length in x - axis } +{ 2 nos. ×( L- bend length)}] - 2nos.× ( 2 times bar dia. for 90° bend.) 

=[ { footing length - 2 × cover } + 2nos.×{ footing height - 2 × cover}] - 2× ( 2 × bar dia. )

= [ { 2000 mm. - 2 × 50 mm. } + 2 × { 300 mm. - 2 × 50 mm. } ] - 2 × ( 2 × 12 mm.)

= [ 1900 mm. + 400 mm ] - 48 mm.

= 2300 mm - 48 mm

= 2252 mm. i.e. 2.252 m.


Cutting length of the bar along the y -direction

=  [ {bar length in y - axis } +{ 2 nos. ×( L- bend length)}] - 2nos.× ( 2 times bar dia. for 90° bend.) 

=[ { footing width - 2 × cover } + 2nos.×{ footing height - 2 × cover}] - 2× ( 2 × bar dia. )

= [ { 1500 mm. - 2 × 50 mm. } + 2 × { 300 mm. - 2 × 50 mm. } ] - 2 × ( 2 × 12 mm.)

= [ 1400 mm. + 400 mm ] - 48 mm.

= 1800 mm - 48 mm

= 1752 mm. i.e. 1.752 m.


Now, we will prepare BBS of the footing, from calculated data.

sl       bar      dia.   no.   length      total     weight         total     
no.    type    mm.            in m.    length    in kg/m       weight       

 1.    x- axis    12     10    2.252      22.52       0.89          20.043    

2.   y - axis   12      14     1.752      24.528      0.89          21.829

                                            Total weight of the bars = 41.872kgs               

                                             Add 2 % wastage            = 0.837kgs

                  The grand total of rebar for footing    =  42.709 kgs.

Note : Weight of 12mm dia bar /meter is 0.89 kg.


                                                                                CONTINUED 👉